Building Response to Tunnelling - 2016

  • Owner: METROPOLITANA MILANESE
  • Client: ASTALDI
  • Country: ITALY
  • Period: 2012- current
  • TECON SOW: Building response analyses for the Underground Line 5

Work description

During the design phase of new Milan Metro Line 5 all buildings crossing the line route were analyzed in order to prevent damages while tunneling.

Building damage due to excavation-induced ground movement is evaluated using a damage criterion based on the average state of strain in the distorting portion of the structure, and by considering the effect of building shear stiffness on the distortions imposed by the ground settlement profile.

For those buildings that after a first-level analysis were considered critical (with a damage class ≥ 2 following Boscardin and Cording Criteria), a more refined analysis is required in order to analyze their exact behavior while tunneling, and, in case, to avoid serious damages with preventive actions.

Tecon services

Second Level Analysis based on three dimensional FEM analyses of several buildings subject to TBM settlement fields.

Download

Building Response to Tunnelling - 2016 (97.19 kB)

Project Categories

TECON srl
Strada 1 Palazzo WTC
20090 - Milanofiori - Assago (MI), Italy
Tel: 02 92882150

P.IVA / Cod.Fisc.: 06503230150
TECON srl non è a socio unico e non è in stato di liquidazione.

Certification
Tecon QMS is certified ISO 9001-2015 by Lloyd’s LRQA