Work description
Pre-feasibility analysis of the types of floating platforms more suitable in the Mediterraneum Seas to provide support for the installation of a 15 MW wind turbine.
Highlights of the main aspects that must be investigated in the project execution phase with the criticalities of the construction supply chain
Tecon services
Screening Phase
Comparisons with "scoring" of the various types (pros and cons of the various types)
- Trends of the last years of the types of platforms
- Materials
- Mooring lines (cables/chains)
- Anchors on the bottom
- Overview of construction and installation
- Technology Readiness Level (TRL)
Analysis Phase
Ship stability/buoyancy checks
- Calculation of stability curves and related regulatory checks
- Determination of hydrodynamic loads
- "Motion Analysis" of the hull
- Determination of ballast
- Calculation of heel angles and limit conditions/regulatory limits
- Calculation of "RAO's"
- "Mooring analysis" with model of mooring lines
- Determination of loads on mooring lines
- Determination of loads on anchors/anchor piles on the bottom
- Preliminary checks of the main structural elements