The Helideck Nexus project represents a sophisticated engineering achievement in offshore helicopter landing facility design and implementation. Commissioned by Samsung and executed through Bayards as the primary client, TECON provided comprehensive detailed design services for the helideck structure installed on the Nexus FPSO vessel. This critical infrastructure component ensures safe helicopter operations for personnel transfer and emergency evacuation in offshore oil and gas production environments.

The project required meticulous engineering to accommodate heavy-duty helicopter operations on a floating production platform. The design needed to support both EH101 and S61N helicopter types, with the EH101 representing the design case at a maximum take-off weight of 14,600 kg (143 tonnes). This substantial load requirement, combined with the dynamic marine environment and integration with existing vessel superstructure, presented significant technical challenges requiring advanced structural analysis and multidisciplinary coordination.

Project Scope

The Helideck Nexus project encompassed the complete engineering design of a 22.8-meter diameter octagonal helideck structure. TECON’s scope of work included the development of detailed engineering solutions across multiple technical disciplines, ensuring the facility met international standards for offshore helicopter operations while maintaining structural integrity in harsh marine conditions.

Structural Engineering

  • Design of primary steel support frame interfacing with the FPSO superstructure deck, engineered to transfer substantial helicopter loads through the existing vessel structure
  • Structural calculations and analysis for the aluminum helideck platform, optimizing material selection for weight reduction while maintaining required strength
  • Connection design between the steel support framework and aluminum landing surface, accounting for differential thermal expansion and dynamic loading
  • Fatigue analysis and dynamic response evaluation under cyclic helicopter landing loads and vessel motion

Safety Systems Design

  • Detailed engineering of the helideck drainage system to ensure rapid removal of water, fuel spills, and firefighting foam from the landing surface
  • Fire water system design including distribution network, deluge systems, and integration with the vessel’s main firefighting infrastructure
  • Safety perimeter design with appropriate edge protection and access systems for maintenance personnel

Technical Compliance

  • Adherence to international helideck design standards including CAP 437 (UK Civil Aviation Authority) and relevant classification society requirements
  • Wind and environmental load analysis for the specific vessel operating location and conditions
  • Coordination with helicopter operating specifications for both EH101 and S61N aircraft types

Engineering Approach

TECON’s multidisciplinary engineering methodology integrated structural, mechanical, and safety systems design into a cohesive solution. The team utilized advanced finite element analysis to optimize the steel support structure, minimizing weight while ensuring adequate load capacity for helicopter operations. The octagonal geometry was selected to provide optimal landing area while efficiently distributing loads to the support points on the vessel superstructure.

The design process involved close collaboration with Bayards and Samsung to ensure seamless integration with the FPSO’s existing systems and structures. Material selection balanced the requirements for corrosion resistance in the marine environment, structural performance under dynamic loads, and weight optimization to minimize impact on the vessel’s overall center of gravity. The final design successfully achieved all performance objectives while maintaining cost-effectiveness and constructability for fabrication and installation during the 2006-2007 project timeline.

Project Data

OWNER
Samsung

CLIENT
Bayards

INSTALLATION VESSEL
Nexus FPSO

PROJECT PERIOD
2006 – 2007

HELIDECK DIAMETER
22.8 m

HELIDECK SHAPE
Octagonal

MAX DESIGN LOAD
143 tonnes

TECON SCOPE
Detailed Design Services

find out more projects

Tolmount Development Project

Milan Metro Line 4

Contact Our Engineers FOR a Professional Consultation

Tecon is an engineering consulting company with over 40 years of experience in offshore, marine and civil structural design.
P.IVA 06503230150
CONTACT US
TECON srl
Strada 1, snc
Palazzo Congressi
20057 Assago (MI), Italy
View on maps Phone:  +39 02 92882150 Fax:  +39 02 92882180
MORE ABOUT US
©2026 Tecon srl. All Rights Reserved.
CREDITS
Privacy Policy
Cookie Policy